PM Glossary

Listed below are a set of commonly used project management terms. If you would like the Technology Program Office to make modifications to this list, please send your recommendations to tpo@berkeley.edu.

Acceptance Criteria: those criteria, including performance requirements and essential conditions that must be met before the project deliverables are accepted.

Activity: an action necessary to achieve a project task and is the smallest unit of project work.

Assumptions: factors that, for project planning purposes, are considered to be true and do not require proof.\Budget: the approved funding estimate for completing the full scope of project work described in the work breakdown structure.

Backlog: Backlog Acts as a repository for requirements targeted for release at some point. These are typically high level requirements with high level estimates provided by the product stakeholders. The requirements are listed on the backlog in priority order and maintained by the product owner.

Business Case: a written document that describes the reasons for initiating a project; it also describes the resources, such as money, staff time, and equipment, that are required to achieve the specific business goals.

Change Control: the process of identifying, documenting, approving or rejecting changes to the project plan.

Communications Management Plan: a document that describes the communications needs for a project. It describes:

Constraint: a restriction which is either internal or external to the project that will restrict the performance of the project. For example, a fixed amount of money allotted for a project budget is a cost constraint, and a set date by which a project must be completed is a time constraint.

Critical Path: the chain of linked dependent project tasks in a project network diagram that has the longest required completion time. The end date of a project is dictated by the tasks that make up this critical chain of tasks. Any change to the time required to complete a task on the critical chain will impact the overall completion date of the project.

Decomposition: a planning method that divides the project scope and deliverables into smaller, more manageable parts, until the work associated with each part is defined in adequate detail so that members of the project team can execute, monitor, and control all of the tasks required to fulfill the project scope.

Deliverable: any measurable, tangible, verifiable outcome, result, or item that must be produced to complete a project milestone.

Duration: the period of time over which a task is completed. The duration of a task may be dependent on or independent of the resources assigned to perform the task. If a task has a fixed duration, its duration is not affected by the amount of resources assigned to the task.

Float (slack): the amount of time that a task in a project network diagram can be delayed without causing a delay to:

An activity that has a total float equal to zero is said to be a "critical activity", which means that a delay in the finish time of this activity will cause the entire project to be delayed by the same amount of time.

Focus Group: a form of qualitative research in which a group of people are asked about such things as the business issues or functionality of a specific service or product.

Gantt Chart: a popular type of bar diagram that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. The tasks and milestones in the Gantt chart are taken from the work breakdown structure of the project. Some Gantt charts also show the dependency relationships between activities and can be used to show the current schedule status of a project.

Iteration or Sprint: A fixed duration period of time where user stories are chosen to work on. The term Sprint comes from the Scrum methodology and is analogous to the term Iteration. A sprint is defined as a 2-4 week increment of development activities that delivers something of value and the end of the increment. External influences are not allowed to change the requirements of the stories being worked on.

Lag: the amount of time after one task is started or finished before the next task can be started or finished.

Lessons Learned: the learning gained from the process of performing a project. Lessons may be learned during any phase of the project and should be documented so other project teams can benefit from the knowledge gained.

Milestone: a scheduled event signifying the completion of a major deliverable or a set of related deliverables. Typically, the project will be divided into five to ten major milestones. Each milestone has a deliverable and a completion date associated with it, and has acceptance criteria in the description of a deliverable.

Portfolio Management: the centralized management of one or more project portfolios, including the identification, prioritization, authorization, management and control of the projects, to achieve specified organizational goals.

Product Owner: The Product Owner represents the voice of the customer and is accountable for ensuring that the Team delivers value to the business. The Product Owner writes customer-centric items (typically user stories), prioritizes them, and adds them to the product backlog. Scrum teams should have one Product Owner.

Program: a group of related projects managed in a coordinated manner to obtain the benefits that could not be achieved by managing them separately.

Progressive Elaboration: the process of continuously improving and refining a project plan as more information becomes available to the project team. This iterative process allows the project team to create better estimates and more complete plans as the project proceeds.

Project: a temporary and one-time undertaking that has the following five characteristics:

Project Acceptance Report: a document that is used to confirm that the deliverables of the project, as stated in the project charter, meet the specified acceptance criteria described in the charter. The official customer for the project evaluates and signs off on each deliverable.

Project Charter: a statement of the scope, objectives, and participants in a project. It provides:

The charter is signed by the sponsor to authorize the project to commence and use the specified resources.

Project Management: the discipline of organizing and managing resources (e.g., people, money, materials, and equipment) in such a way that the project meets:

Project Management Office (PMO): a department that an organization can establish to define and maintain the standard practices that it uses for project management. By introducing standardized and repeatable practices, the PMO seeks to improve the success of an organization's projects. A PMO is also the source of documentation, guidance, and metrics on the practice of project management. It may also be responsible for centrally managing projects under its supervision and helping an organization's leadership to evaluate proposed strategic projects.

Project Management Professional (PMP): a certification in project management offered by the Project Management Institute.

Project Manager: a temporary position held by the person responsible for the overall project management process and ultimately, for the success of the project. The project manager has the following responsibilities: